Back Frame; Floor; Work Space - Sony ZRD-1 Installation Manual

Hide thumbs Also See for ZRD-1:
Table of Contents

Advertisement

Operation
. Do not block a ventilating hole when operating the display controller.
. When cleaning the display controller, wipe it using fully squeezed cloth, moistened with a neutral
detergent.
Never use a solvent such as benzene or thinner.

1-4-3. Back Frame

. Design a back frame in consideration of possible safety measures.
. Design a back frame that has a horizontal/vertical adjustment mechanism so as to attach the back frame in
high precision.
. It is recommended to connect the ground to back frame.
. Take necessary measures to prevent rust from occurring in all frame steel products.

1-4-4. Floor

Withstand load of floor:
The floor should be strong enough to prevent the distortion or deformation when it is subjected to the
following load.
Mass of display unit (10 kg per unit) x Number of display units + Total mass of bases + Total mass of
back frames + Mass of display controller (6.3 kg per unit) x Number of display controllers
For the distortion, refer to the specifications described in "Rigidity" in "1-3-1. Base".

1-4-5. Work Space

. Design the back frame so that it does not interfere the maintenance of display unit. It is recommended
to secure 1 m or more space in back of the display unit because the service personnel removes the rear
cover to do the service work.
. Design the rolling tower required for the installation and service work so that it does not interfere the
maintenance of display unit.
. Provide sufficient space to install the rolling tower in front of the array in order to clean the surface of