UPS System Installation
Pallet
Figure 4-4. Removing the UPM Section Right Side Shipping Bracket
4.3
Mechanically Joining the Sections
NOTE
The following procedure permits the UPS sections to be installed in a location
where there is limited space to slide the sections together from the sides.
NOTE
For the following steps, verify that the forklift or pallet jack is rated to handle the
weight of the section (see Table 3-1 for cabinet weight).
1.
Using a forklift, move the UPM section to the final installed location.
2.
Remove one top screw and two bottom screws securing the UPM section wireway panel (see Figure 4-5).
Lift the panel straight up to remove it from the panel hanger brackets at the top of the cabinet.
3.
Remove the screws securing the top and bottom internal safety shield panels and remove the panels.
Retain the hardware for later use.
4.
Remove the screws securing the corner channel and remove the channel (see Figure 4-5). Retain the
hardware for later use.
®
4-6
Eaton
Power Xpert
Right Side Shipping
Bracket
®
9395P-900 UPS Installation and Operation Manual P-164000501—Rev 09
Shipping Bracket
Bolts
www.eaton.com/powerquality
Shipping Bracket
Bolts