Battery Power Wiring - Eaton Power Xpert 9395P-900 Series Installation And Operation Manual

High performance ups
Hide thumbs Also See for Power Xpert 9395P-900 Series:
Table of Contents

Advertisement

UPS System Installation
4.8.2

Battery Power Wiring

When sizing the battery system, do not exceed the internal battery charger capabilities. See
Chapter 10, "Product Specifications" for maximum battery charger currents.
Lors de l'évaluation du système de batterie, ne pas dépasser les capacités internes du chargeur de
batteries. Se reporter au chapitre 10 sur les notices techniques pour connaître les tensions
maximales du chargeur de batteries.Ne pas installer une armoire endommagée. Signaler les
dommages au transporteur et communiquer avec un représentant du service Eaton
immédiatement.
To install wiring to connections:
NOTE
NOTE
1.
Route the battery cables between the ISBM section and the battery system or battery disconnect. See
Figure 4-16, Figure 4-17, Figure 4-19, and Figure 4-20 for wiring access information and terminal locations.
2.
If wiring the UPS for a common battery, proceed to Step 3; if wiring for a separate battery, proceed to
Step 5.
3.
Using hardware from the external wiring terminal hardware kit (see Table 3-20), connect the positive,
negative, and ground DC power wiring from the battery system or disconnect to the ISBM section battery
and ground terminals. Use both sets of terminals shown in Figure 4-19 as needed. See paragraph 3.2.3 for
wiring and termination requirements.
4.
Proceed to Step 6.
5.
Using hardware from the external wiring terminal hardware kit (see Table 3-20), connect the positive,
negative, and ground DC power wiring from the battery systems or disconnects to the ISBM section
battery and ground terminals. Use one set of terminals for each UPM. See paragraph 3.2.3 for wiring and
termination requirements.
6.
After wiring the UPS system to the facility power and critical load, be sure to ground the system according
to local and/or national electrical wiring codes.
7 .
If wiring interface connections, proceed to paragraph 4.9; otherwise, proceed to Step 8.
8.
When all wiring is complete, reinstall the top and bottom safety shield panels removed in paragraph 4.8.1,
Step 2. Secure with the retained hardware.
9.
Reinstall the left front panel removed in paragraph 4.8.1, Step 1 and secure with the retained hardware.
®
4-24
Eaton
Power Xpert
An installed FI-UPM is always designated as UPM 4.
Battery Cable Routing Requirements using Conduit:
Each conduit must have a Positive, Negative, and Ground conductor
l
There must be an equal number of positive and negative conductors in a single
l
conduit. Only one ground conductor is required in each conduit.
Battery Cable Routing Requirements using Raceway:
Positive and negative battery cables must be run side by side in the raceway in an
l
alternating pattern (+ - + - + - + -).
There must be a ground cable running in the raceway with the battery cables.
l
®
9395P-900 UPS Installation and Operation Manual P-164000501—Rev 09
CAUTION
ATTENTION!
www.eaton.com/powerquality

Advertisement

Table of Contents
loading

Table of Contents