Commissioning

2.8 First commissioning, control mode vector AC Drive in the booksize format

2.8
First commissioning, control mode vector AC Drive in the booksize
format
An example provided in this chapter explains all the configuration and parameter settings, as
well as tests that are required for initial commissioning. Commissioning is carried out using
the STARTER commissioning tool.
Preconditions for commissioning
1. The commissioning preconditions (Page 15) have been met.
2. The commissioning checklists (Page 17) (Tables 1-1 and 1-2) have been completed and
3. The STARTER commissioning tool is installed and activated.
4. The drive system has been wired according to the specifications.
5. The communication between the PG/PC and drive system has been prepared.
6. The power supply of the Control Unit (24 V DC) has been switched on.
2.8.1

Task

1. A drive unit is to be commissioned (operating mode "Vector", closed-loop speed control),
2. Commissioning is performed using the BOP20.
3. The function keys on the BOP20 must be parameterized so that the ON/OFF signal and
128
the points fulfilled.
– see the "Readme" file on the STARTER installation DVD
without DRIVE-CLiQ and without speed encoder with the following components:
Designation
Component
Closed-loop control
Control Unit
Control Unit 310-2 DP
Operator Panel
Basic Operator Panel BOP20
Infeed and drive
Power Module
Power Module 340
Motor
Induction motor
(without DRIVE-CLiQ interface)
speed settings can be defined via these keys.
Order number
6SL3040-1LA00-0AA0
6SL3055-0AA00-4BAx
6SL3210-1SB14-xxxx
1LA7
Commissioning Manual, (IH1), 01/2012, 6SL3097-4AF00-0BP2
Commissioning Manual