What to do?
6.3
Ramp-function
generator
6.4
Setpoint
7
Save the
parameters on the
device
8
The motor starts to
run.
Commissioning Manual
Commissioning Manual, (IH1), 01/2012, 6SL3097-4AF00-0BP2
2.6 First commissioning control mode vector U/f in booksize format
Ramp-function generator
p1140 = 1 Ramp-function generator enable
p1141 = 1 Ramp-function generator start
p1142 = 1 Enable setpoint
Specify setpoint
p1001 = 40 Fixed setpoint 1
1. Select the drive unit in the project tree.
2. Call the "Connect target device" shortcut menu.
3. Call the "Target device > Load to target device" shortcut
menu.
The option "After loading, copy RAM to ROM" is active.
Click on "Yes" to confirm backup.
or
4. Call the shortcut menu "Target device > Copy RAM to ROM".
The drives can be started via the control panel in STARTER.
Line/DC link identification will be carried out once
the pulses for the infeed have been enabled and line/DC link
identification has been activated. The infeed then switches
into the "Operation" state.
Once the pulses are enabled, a one-off motor data
identification run (if activated) is carried out.
When the pulses are enabled again, optimization with a
rotating motor is carried out, if this is activated.
How to do it?
Commissioning
Comment
See function diagram
[3060]
See function diagram
[3010]
Position cursor on drive
unit (SINAMICS S120) and
right-click.
For more information about
the control panel, see
Getting Started.
During motor data
identification, a current
flows through the motor,
which means that it can
align itself by up to a
quarter of a revolution.
For more information about
line/DC link/motor data
identification, see the
Function Manual.