Commissioning
5.6 Commissioning with STARTER
To complete the basic commissioning of the Inverter, the following tasks must be completed:
● Ensure that the Inverter and motor are powered-up (no run command should be issued).
● Ensure that the Inverter is correctly connected to the PC, using the appropriate
communications cable.
In the project tree under commissioning, select "Control panel". The control panel will appear
at the bottom of the screen.
Image 5-18
Press the Start [I] button and the motor calculation will be performed. When this has been
completed, the basic commissioning of the Inverter and motor has been completed.
Image 5-19
78
Control panel activation
STARTER control panel
Operating Instructions, 07/2016, FW V3.63, A5E36768472B AB