Compaq ProLiant 5500 Setup And Installation Manual page 44

Pentium ii xeon and pentium iii xeon processor-based servers
Hide thumbs Also See for ProLiant 5500:
Table of Contents

Advertisement

3-12
Rack-Mount Server Installation
4.
Extend the inner slide from the front of the bracket rail. With this piece
extended, you will see two screw holes aligned in the mounting bracket
and the bracket rail. These are the two exposed holes near the back end
of the bracket rail and the front hole accessible through a slot in the
inner slide.
5.
Fasten the bracket rail to the mounting bracket with two 8-32 x 1/4-inch
slotted screws. (Do not use nuts or washers with the screws.)
See step 1 of the following figure.
6.
Adjust the inner slide to access the other two screw holes, one at a time,
through the slotted opening in the inner slide. Use two more 8-32 x 1/4-
inch slotted screws to fasten the bracket rail to the mounting bracket.
See steps 2 and 3 of the following figure.
The following figure shows inserting the screws into the appropriate holes. The
screws will line up with the 26-inch markings stamped along one edge of the
mounting bracket. These marks identify the mounting holes for the 26-inch
slides used in Compaq racks. (The other markings stamped along the opposite
edge are for use with slides that support other servers.)
For use with Pentium II Xeon and Pentium III Xeon processor-based servers only

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Proliant 5500r

Table of Contents