UPS MAINTENANCE
10. Replace the EBM front cover.
11. Verify that all wiring connecting the UPS and EBM(s) is installed

Testing New Batteries

To test new batteries:
1.
2.
3.
66
Avaya 9130 1000–3000 VA UPS Site Preparation, Installation and Operator's Manual
To replace the cover, verify that the EBM cables are routed through
the EBM cover knockouts, then slide the cover from the left to the
right until it connects with the cover hook near the left side of the
EBM cabinet. Reinstall the two screws on the right side of the front
cover. For reference, see Figure 21 on page 64.
Repeat for each additional EBM.
behind the front covers and is inaccessible to users.
Plug the UPS into a power outlet for 48 hours to charge the
batteries.
Press any button to activate the menu options.
Select CONTROL then START BATTERY TEST.
The UPS starts a battery test if the UPS is in Normal mode with no
active alarms and the bypass voltage is acceptable.
During the battery test, the UPS transfers to Battery mode and
discharges the batteries for 25 seconds. The front panel displays
"Battery test running" and the percentage of the test completed.