6. PUTTING INTO SERVICE

6.1 FINAL CHECKS

1. If foot traffic cannot be excluded, check that
the forces generated by the beam fall within
the limits permitted by the standard. Use an
impact force tester in accordance with standards
EN 12453. For non-EU countries, of there are
no specific local regulations, the force must be
less than 150 N. Check that the maximum force
required to move the beam by hand is less than
220 N.
2. Check the automation system is working properly
with all the devices installed.
1
A
A
B680H

6.2 INSTALLING THE CABINET

With reference to 27 :
1. Insert the cabinet and secure it to the body of the
automation using the screws A.
2. Secure the spacer B to the strip C using the screw D.
3. Insert the two spacers E and fasten them to the
cabinet using the screws F.
4. Insert the strip C and secure it to the cabinet using
the screw G.
2
C
E E
F
F
44
3
C
B
D
C
C
G
27
732719 - Rev.E

Advertisement