Connect to Guy Collar
15. Remove the four guy line spools from the guy bag. Connect the single-line, hook ends
from the bottom, to the four larger, guy plate holes at 90° angles.
Figure 4-57 Guy Lines
16. Let enough slack out of each guy line and place the spools on the ground about 10 ft / 3
m from the center of the tripod in the general area where the stakes will be driven.
Ensure that the lines are free of obstructions and snags. Check that the guy lines will not
hit the payload as it is raised. If you are raising the mast during windy conditions, the
mast will need to be guyed as you raise the mast.
4.6.2.2 Complete Tripod Installation
Fully Raise the Tripod Legs
38. As a team, unlock the leg clamps, step on the leg bases, and lift the tripod until the
nested legs drop and are fully extended. Lock the leg clamps.