Stage the Guy Lines
20. For masts 44 ft / 13.4 m to 60 ft / 18.3 m tall, prepare the guy lines for a tube to be
breech loaded by loosening a maximum of 5 ft / 1.5 m of guy line from each tensioner.
SINGLE LINE
SIDE
DOUBLE
LINE SIDE
Add Slack to Winch Cable
21. Since the cable pulley is attached to the tip tube, the cable must be adjusted before each
tube is breech loaded. Before loading a tube, add slack to the cable line by turning the
winch handle clockwise. This allows the pulley to be raised when the tubes are breech
loaded. Ensure that the winch line is free of obstructions and snags.
Figure 4-69 Cable Path Shown in Red
4-28
'
M
S
ANUAL
HOOK (NOT
VISIBLE)
GUY STAKE
Figure 4-68 Prepare Guy Lines
SINGLE LINE SIDE
Figure 4-70 Add Slack to Cable
DOUBLE
LINE SIDE
GUY STAKE