3.4.7 Battery Modules and Control Module (BMS) Pile up

Danger: When battery is connected together with the base, the internal socket still has
high voltage DC power from serial connected battery modules.
1. After installation of the battery module, lift up the control module (BMS), adjusting to make its
connector align with the connector of the battery module.
2. Slowly place down the control module (BMS) on the installed battery module.
NOTE
: The above picture is just for reference. The quantity of the battery modules is based on
your practical system.