Removal Procedure (cont'd)
7.) Perform the following functional tests. If all are successful, include the debrief script provided below.
Table 8-41
Service Manual
Section 4-3-1
Section 4-3-2
Section 4-8-2-6
Section 10-5-5
8-6-6-5
Mounting procedure
Install the new parts in the reverse order of removal.
2
Functional Tests
Section
Functional Test / Diagnostic Test
Chapter 8 Replacement Procedures
Power On/Boot Up
Power Off / Shutdown
Bumper Set
Physical Inspection
LOGIQ™5 S
ERVICE
Debrief Script
"Service Manual, Direction
2300000, Rev 1+, Section 8-6-6. Equipment