Step 5: Manage the cabling

A. Use cable clips or tie wraps to attach the cable to the racking.
Leave no more than 1.8 m (six feet) between cable clips or tie
wraps.
B. Dress any excess cabling in loops so that it does not contact
the roof. Do not form loops smaller than 12 cm (4¾ ") in
diameter.
WARNING: Tripping Hazard. Loose cables can become a
tripping hazard. Dress the IQ Cable to minimize this potential.

Step 6: Connect the microinverters

A. Connect the microinverter. Listen for a click as the connectors engage.
B. Cover any unused connector with Enphase Sealing Caps. Listen for a click as the
connectors engage.
WARNING: Risk of
electric shock. Risk of
fire. Install sealing caps
on all unused AC
connectors, as these
connectors become
live when the system is
energized. Sealing caps
are required for
protection against
moisture ingress.
NOTE: If you need to remove a sealing cap, use the IQ Disconnect Tool. See
Disconnect a Microinverter
20
IQ7/IQ7+/IQ7X/IQ7A Microinverters Installation and Operation Manual
for more information.
© 2023 Enphase Energy Inc. All rights reserved.
Cable clip
September 2023
IOM-00028-1.0