Step 5: Manage the cabling

A. Use cable clips or tie wraps to attach the cable to the racking. The IQ Cable must be
supported at least every 300 mm.
B. Dress any excess cabling in loops so that it does not contact the roof. Do not form loops
smaller than 120 mm in diameter.
WARNING: Dress the excess IQ Cable to avoid the risk of cable insulation abrasion against
the roof surface.

Step 6: Connect the microinverters

A. Connect the IQ Cable to the microinverter. Listen for a click as the connectors engage.
B. Seal any unused connector on the IQ Cable with IQ Sealing Cap. Listen for a click as caps
engage.
WARNING: Risk of electric shock. Risk of fire. Install IQ Sealing Caps on all unused AC
connectors as these connectors become live when the system is energized. IQ Sealing
Caps are required for protection against moisture ingress.
NOTE: If you need to remove an IQ Sealing Cap, you must use the IQ Disconnect Tool.
18
IQ8P Microinverter Installation and Operation Manual
Cable clip
© 2023 Enphase Energy Inc. All rights reserved.
September 2023
IOM-00001-1.0

Advertisement

Table of Contents
loading

This manual is also suitable for:

Iq8p-72-2-int

Table of Contents