Step 3: Mount the microinverters

A. Mount the microinverter horizontally, bracket side up or vertically.
WARNING: Install the microinverter under the PV module to avoid direct exposure to
rain, UV, and other harmful weather events. Do not mount the microinverter upside
down.
B. Torque the microinverter fasteners as follows. Do not over-torque.
Horizontal mount
DC connector
Vertical mount
18
IQ7/IQ7+/IQ7X/IQ7A Microinverters Installation and Operation Manual
Always place the microinverter under the PV module, protected from direct
exposure to rain, sun, and other harmful weather events. Allow a minimum of
1.9 cm (3/4") between the roof and the microinverter. Also, allow 1.3 cm (1/2")
between the back of the PV module and the top of the microinverter.
For vertical mount, maintain > 30 cm (12") clearance from the edges of the PV
module to protect the microinverter from direct exposure to rain, UV, and
other harmful weather events.
6 mm (¼") mounting hardware: 5 N m (45 to 50 in-lbs.)
8 mm (5/16") mounting hardware: 9 N m (80 to 85 in-lbs.)
When using UL 2703 mounting hardware, use the manufacturer's
recommended torque value.
© 2023 Enphase Energy Inc. All rights reserved.
AC connector
September 2023
IOM-00028-1.0

Advertisement

Table of Contents
loading

This manual is also suitable for:

Iq7+Iq7xIq7a

Table of Contents