Commissioning

9
Commissioning
9.1

Function check

Before commissioning the device, make sure that the post-installation and post-connection
checks have been performed.
• "Post-installation check" checklist (→  19)
• "Post-connection check" checklist (→  28)
9.2

Switching on the measuring device

If the post-installation checks have been performed successfully, switch on the supply voltage.
The device is now operational.
The measuring device performs a number of post switch-on self-tests. Measuring mode
commences as soon as startup completes.
If startup fails, an error message to this effect is displayed in the DeviceCare or FieldCare
operating program, depending on the cause.
9.3

Configuring the measuring device

The Setup menu with its submenus contains all the parameters needed for standard
operation.
Navigation
"Setup" menu
Setup
30
Device tag
Device tag
System units
Communication
Status input
Batch output
Pulse/frequency/switch output 1 to 2
Dosimag
(→  31)
(→  31)
(→  32)
(→  34)
(→  34)
(→  36)
Endress+Hauser

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Dosimag and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents