4.13 PLACING THE BOILER BACK IN SERVICE AFTER A
PROLONGED SHUTDOWN
After a prolonged shutdown (one year or more), the following procedures must be followed:
Placing the Boiler Back In Service After Prolonged Shutdown Instructions
1. Review installation requirements included in Section 2 of the Benchmark 5000 – 6000
Installation and Startup Guide, OMM-0117 (GF-202).
2. Inspect all piping and connections to the unit.
3. Inspect exhaust vent and air inlet duct work (if applicable).
4. Perform initial startup procedures in Section 4: Initial Startup of the Benchmark 5000 –
6000 Installation and Startup Guide, OMM-0117 (GF-202).
5. Perform safety device testing procedures in Section 5: Safety Device Testing of the
Benchmark 5000 – 6000 Installation and Startup Guide, OMM-0117 (GF-202).
6. Perform scheduled maintenance procedures as described in Section 4: Maintenance of
this guide.
IMPORTANT!
The blower can be damaged if it is unused for a prolonged period of time. If this occurs, it is
critical that you complete the instructions for Long Term Blower Storage in Appendix J.
Failure to complete these instructions will void all warranties.