Returning The Boiler To Service After Shutdown - Watts AERCO Benchmark BMK750 Operation And Service Manual

With edge (i) controller
Hide thumbs Also See for AERCO Benchmark BMK750:
Table of Contents

Advertisement

Benchmark with Edge [I]: Operation-Maintenance Manual
SECTION 8 – MAINTENANCE

8.12 RETURNING THE BOILER TO SERVICE AFTER SHUTDOWN

After a prolonged shutdown (one year or more), the following procedures must be followed:
Placing the Boiler Back in Service After A Prolonged Shutdown Instructions
1. Review installation requirements included in Section 2 of the Benchmark 750-6000 with
Edge [i]: Install-Startup Manual (OMM-0144, GF-217).
2. Inspect all piping and connections to the unit.
3. Inspect exhaust vent and air inlet duct work (if applicable).
4. Perform initial startup per Section 4 of this guide.
5. Perform the instructions in Section 5: Safety Device Testing, above, and all scheduled
procedures described Section 8: Maintenance.
OMM-0145_A99 • GF-218 •
Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST
9/18/2019
Page 141 of 157