8.14

Procedures: Pressure Indicator Modules (PM 620)

Do the procedure as follows:
1. Assemble the pressure indicator with the necessary
PM620 modules
2. Connect the instrument to the pressure standard
3. Let the equipment get to a stable temperature
(minimum: 60 minutes since the last power on)
4. Use the calibration menu (Ref: Section 8.1) to do a two-
point calibration
• Zero and +FS for absolute sensors
Note: If software version requires a three-point
calibration for an absolute sensor, use points at 0, 50%
and +FS or three-point calibration:
• -FS, Zero and +FS for gage sensors
• (Ref: Table 8-17)