INSTALLATION
Figure 2.15 Ethernet Communication Cable Wiring
Step 10 Install ethernet communication cable, as shown in Figure 2.15. It won't be
needed if the WiFi module will be used.
NOTE:
After the wiring harness is installed, the waterproof connector must be tightened
with a torque of 5 Nm±10%.
NOTE:
The ethernet communication cable can be connected wiring directly through the
gum-elastic ring of the M32 waterproof contact, no need to make the on-site
network cable. The maximum outer diameter of the network cable does not
exceed 14mm.
Figure 2.16 Install WiFi Module
Step 11 Install WiFi module, as shown in Figure 2.16.
13
14
NOTE:
Please tighten the screws here with the torque of 2 N.m±10% to avoid problems
such as poor signal.
NOTE:
If using WiFi module, open the cover plate of the side WiFi module, insert the
WiFi module into the terminal port and then fix it with screws by using T20
double offset ring spanner, as shown in Figure 2.16. The suggested torque is 1.6
N.m±10%
If you will install external M4856-P for expansion, please go to section
2.4.4 directly.
Step 12 The wiring is completed, please re-cover the B3 upper cover plate and use the
T20 double offset ring spanner to tightly lock the upper cover screw. The suggested
torque is 2.8 N.m±10%. Then install the white plug, as shown in Figure 2.17.

2.4.4 Battery Expansion

If you are not installing external M4856-P battery for expansion, please neglect this
section.
1 x Battery Pack
6 X M5 * 10 Screw
1 x Positive power line
1 x Negative power line
Figure 2.18 Parts List of M4856-P Accessory Package
Figure 2.17 Re-cover the Upper Cover Plate
1 x PE Protective Bag
2 X M4 Flange
1 X Communication Cable
INSTALLATION
1 x Expansion Bracket
4 X Expansion Screw
1 x User Manual
1 x Quick Installation manual

Advertisement

Table of Contents
loading

Table of Contents