Figure 5-23 Installing battery communications cables
Step 5 Open the battery terminal protective cover and install battery copper bars and
cables.
● Install copper bars between the battery modules, and then install cables
● Connect the round hole of the copper bar to the upper battery module, and
● After the copper bar on each terminal is secured, reinstall the protective cover
● Battery cables are preinstalled inside the cabinet.
● Excessive bolts will be used as spare parts.
Issue 09 (2023-03-26)
NO TICE
between the battery modules and the BCU.
then connect the waist hole of the copper bar to the lower battery module.
on the terminal.