Preparations for start-up

Preparations for start-up

6-2

Before you start!

What you should know!
The preparation includes activities that are not necessary to be carried
out on a daily or weekly basis. One exception to this is the visual check.
The visual check should be part of your daily measuring operation rou-
tine.
Initial start-up by a service engineer
Initial start-up is carried out by a ZEISS service engineer. However, you
must familiarize yourself with the preparations required for start-up as
well as know and follow the corresponding safety instructions.

Connecting the power supply

The electrical power supply must be close to the installation site to allow
connecting the power supply to the CMM. The corresponding measures
must be taken before installing the CMM. See electrical data.
NOTE
For more information on the electrical power supply, please refer to the
»Installation site requirements« brochure.

Connecting the compressed air supply

The compressed air supply system needs to be close to the CMM to en-
able its connection to the CMM supply line. The corresponding mea-
sures must be taken before installing the CMM.
– Please observe the requirements of the compressed air supply.
NOTE
For more information on setting up the compressed air supply, please
refer to the document entitled »Installation site requirements«.
Compressed air connection on the CMM
The compressed air connection is located on the rear side of the CMM.
Adjusting the pressure
The pressure is adjusted individually for each installation by a ZEISS ser-
vice engineer during initial start-up. After this, the pressure must not be
readjusted.