Installation
Manual
LTP LCR/124HW HLK MAN 2020 Edition v2.1
For Model:
LTP LCR/124HW Top of Pole Mount
With added High Load Kit
NOTE: When adding this High Load Kit to the LTP LCR/124HW top of pole mount, use this
manual for assembly and disregard the manual that comes with the main mount kit.
LTP HW
Mount
Series

Advertisement

Table of Contents
loading

Summary of Contents for Tamarack Solar LTP HW Mount Series

  • Page 1 LTP HW Mount Series Installation Manual LTP LCR/124HW HLK MAN 2020 Edition v2.1 For Model: LTP LCR/124HW Top of Pole Mount With added High Load Kit NOTE: When adding this High Load Kit to the LTP LCR/124HW top of pole mount, use this manual for assembly and disregard the manual that comes with the main mount kit.
  • Page 2: Table Of Contents

    Mount can support installations in a wide range of locations. Customer Support Tamarack Solar makes every effort to ensure your mounting kit is easy to install. If you need assistance at any point in your installation or have suggestions on how we can improve your experience, call...
  • Page 3: Tools Required

    LTP HW Mount Series NOTE: References to physical direction in this manual, such as “north” and “south”, apply to installations in the Northern Hemisphere. For installations in the Southern Hemisphere, reverse these physical directions. Tools Required Tools that support the following size hex heads: Torque values are “dry”, add 15% if using anti seize lubricant on stainless steel hardware (Recommended).
  • Page 4 LTP HW Mount Series LTP LCR/124HW WITH HIGH LOAD KIT HARDWARE BAGS LIST & KIT CONTENTS BAG PART PART BAG PART PART DESCRIPTION QTY. DESCRIPTION QTY. NUMBER NUMBER NUMBER NUMBER Kit, 1/2 x 1.25 (5) Set 29-5002-200 Kit, Spare Hardware 29-5007-010 Galvanized Bolt, 3/8-16 x 1.0...
  • Page 5: Step 1: Pre Assembling The Aluminum Pv Module Support Rails

    LTP HW Mount Series Pre Assembly for Model LTP LCR/124HW with High Load Kit NOTE: Some parts and hardware come from both the High Load Kit and the basic mount. The following steps supersede some of the steps in the instruction manual included with the mount this High Load Kit is being installed onto.
  • Page 6 LTP HW Mount Series Detail A: C. Tighten the 5/16” 18 x 7/8” hex bolts, flat washers, and flange nuts to 144 in lbs (dry) and set these assemblies aside. D. Next, assemble the two double rail units. Each unit will consist of two 56” Module Support Rails, two 68”...
  • Page 7: Step 2: Pre Assembling The Galvanized Steel Cross Rails

    LTP HW Mount Series Detail B: E. Tighten the 5/16” 18 x 78” bolts, flat washers, and flange nuts to 144 in lbs (dry) and set these sub assemblies aside. Step 2: Assembling the Galvanized Steel Cross Rails Note: The LTP LCR/124HW Kit will contain six 66” Cross Rails (galvanized steel) and three Connectors, and the High Load Kit will contain two additional 66”...
  • Page 8 LTP HW Mount Series Detail C: B. To make the double rail assembly, lay four of the Cross Rails end to end and back to back, as shown in Detail D. Make sure that the sides with the obround slots all face up. Place two rail connectors, one on each side, in the open sides of the rails, centered on the seam between the two rail halves, and with their flanges down, as shown in Detail D.
  • Page 9: Step 3: Pre Assembling The Aluminum Upper Cross Rail

    LTP HW Mount Series Detail D complete: Step 3: Assembling the Aluminum Upper Cross Rail There are two 66” aluminum Upper Cross Rails included, used with the supplied aluminum Connector to assemble one 132” Upper Cross Rail assembly. A. Lay the two 66” Upper Cross Rails end to end, with the obround slots facing up, the open sides facing the same direction.
  • Page 10: Step 4: Connecting Pv Modules To Module Support Rail Assemblies

    LTP HW Mount Series Step 4: Connecting PV modules to Module Support Rail assemblies: The LTP LCR/124HW mount, with the added High load Kit, utilizes three PV modules per column, two columns side by side. For assembly purposes, attach the middle PV modules only at this point, one to each pair of Module Support Rails, as shown in Detail F.
  • Page 11 LTP HW Mount Series A. Lay one of the PV modules on a flat surface, frame side up as shown in Detail F B. Place one doubled and one single Module Support Rail assembly across the PV module with the obround slots in the rails face down on the module frame, and the open side of the single rail assembly facing towards the center of the module, as shown in Detail F.
  • Page 12: Step 5: Attach Pole Clamp Assembly To Top Of Pole

    LTP HW Mount Series Step 5: Attach Pole Clamp assembly to Top of Pole A. Loosen the four 1/4" bolts on the top of the Pole Clamp slightly to allow enough slack for the Clamp halves to slip over the top of the pole and slide the pre assembled Pole Clamp unit over the pole. The top edges of the pole should fit into the notches of the Pole Clamp assembly (see Detail G).
  • Page 13: Step 6: Attach Tilt Plate Mounting Channels

    LTP HW Mount Series Step 6: Attach Tilt Plate Mounting Channels A. Place the two Tilt Plate Mounting Channels on the sides of the Pole Clamp assembly as shown in Detail I. Also note the “helpful tip” in Detail I. B.
  • Page 14: Step 7: Attach Tilt Plates

    LTP HW Mount Series Step 7: Attach Tilt Plates A. Attach Tilt Plates, with the flanges facing to the outside as shown in Detail J, using the six 1/2” 13 x 1.25” bolts (three for each Tilt Plate), flat washers, lock washers and nuts. Position the Tilt Plates with the top level (0°...
  • Page 15: Step 9: Attach Pv Module Support Rail Sub Assemblies To Cross Rails

    LTP HW Mount Series Detail K: Step 9: Attach PV Module Support Rail Sub Assemblies to Cross Rails A. Lean one of the 124” module support sub assemblies (with the single center PV module attached) against the cross rail, as seen in Detail L, with the 56” Rail sections on the north end, the doubled rail assembly to the inside (near the pole) and with the PV module’s wiring junction box in the proper location for final wiring.
  • Page 16 LTP HW Mount Series Detail L: B. Place the seam, where the 56” and 68” Module Support Rails meet, centered between the two Cross Rail assemblies. C. Place the inside edge of the PV module near the center of the Cross Rails (where the seam is between the two connected Cross Rails).
  • Page 17 LTP HW Mount Series D. Drop eight 3/8” x 1” bolts with flat washers into the appropriate slots in order to bolt the Module Support Rails down to the Cross Rails as shown in Detail N. There will be three bolts on each side of the doubled Module Support Rail.
  • Page 18: Step 10: Install Upper Cross Brace And Knee Brace Rails

    LTP HW Mount Series H. Install the under module clamps to the outer rail of the doubled Module Support Rails as shown in Detail O. Detail O: (viewed from underside) Step 10: Install Upper Cross Brace and Knee Brace Rails A.
  • Page 19 LTP HW Mount Series B. Repeat across the south end of the Module Support Rails, using the third set of Cross Rails previously pre assembled (see Details Q and R). This will act as the Knee Brace Cross Rail. Install with the open side of the Rail assembly facing the pole, and the same distance in from the ends as the other Cross Rails.
  • Page 20: Step 11: Adjust Tilt Angle ……………………………………………………………………………………………………

    LTP HW Mount Series Step 11: Adjust Tilt Angle A. Remove the lower two 1/2" 13 x 1.25” bolts from the Tilt Plates and tilt the array to the desired angle. The array tilts in 10° increments from 0° to 60°. Re install the 1/2" 13 bolts and torque all six bolts (three per Tilt Plate) to 40 ft lbs.
  • Page 21 LTP HW Mount Series C. Loosely attach the Outer Swivel Brackets to the Lower Knee Brace Clamp with the (previously set aside) 5/16” 18 x 1” bolt, flat washer, and flange nut, as shown in Detail U. Note: The flanges on both brackets need to face to the outside as shown in Detail U. Detail U: D.
  • Page 22 LTP HW Mount Series F. Loosely attach the two 39.5” Outer Knee Brace Channels to the Outer Swivel Brackets on the Lower Knee Brace Clamp (on the pole), with the open sides facing in, as shown in Detail W, using the 5/16”...
  • Page 23 LTP HW Mount Series H. Connect the Inner Knee Brace Channels to the Outer Knee Brace Channels, as shown in Detail Y, using the 5/16” 18 x 7/8” bolts, flat washers, and flange nuts, in the holes nearest to each end of the Inner and Outer Channels (see Detail Y).
  • Page 24 LTP HW Mount Series Finished Detail:...
  • Page 25: Foundation Hole Guidelines

    LTP HW Mount Series Foundation Hole Guidelines The suggestions below are recommendations only. It is the installer’s responsibility to validate foundation parameters prior to installation, as local geotechnical report may be required to assess soil conditions. We recommend consulting with a local engineer familiar with local regulations and build site requirements, including soil conditions, terrain, and load criteria (wind, snow, seismic).
  • Page 26 LTP HW Mount Series Installation Recommendations: Concrete to be min 3,500 PSI 1. Auger hole to minimum depth shown in foundation guidelines, + 6" for (#2). Drilled holes to be filled with concrete shall be cleaned to remove all loose cuttings. 2.
  • Page 27: Installer Responsibility