Step 9: Attach PV Module Support Rail Sub Assemblies to Cross Rails

A. Lean one of the 124” module support sub assemblies (with the single center PV module attached)
against the cross rail, as seen in Detail L, with the 56” Rail sections on the north end, the doubled
rail assembly to the inside (near the pole) and with the PV module’s wiring junction box in the
proper location for final wiring. Lift the bottom end up and slide the sub assembly onto both Cross
Rails.
Note: Make sure that the 56” sections of Module Support Channels are on the north end of the
two Cross Rails, and that the doubled Module Support Rail assembly is toward the inside near
the pole. Make sure that the PV module wiring junction box is in the proper location for wiring. If
all three of those directives are not present, either the assembly was not done correctly, or this
particular assembly needs to go on the other side of the pole.