B. Repeat across the south end of the Module Support Rails, using the third set of Cross Rails
previously pre assembled (see Details Q and R). This will act as the Knee Brace Cross Rail. Install
with the open side of the Rail assembly facing the pole, and the same distance in from the ends as
the other Cross Rails.
Note: the location of this Knee Brace Cross Rail assembly is determined by the final desired angle
setting for the array, as seen in the table in Detail Q.
Detail R:
Detail Q:
18
LTP HW
Mount
Series