GE FGC TLE Series Manual page 390

40-150 kva/kw, 480 vac three phase highly efficient and scalable
Table of Contents

Advertisement

TLE Series 625 - 750 - 1000
Power connection bus bars configuration for the top cable entry or bottom cable entry
The configuration of the TLE Series 625 - 750 - 1000 is with top cable entry as standard (see Fig. 4.9-3).
It is possible to configure the bus bars with bottom cable entry (see Fig. 4.9-4).
TLE Series 625 & 750
TLE Series 1000
Fig. 4.9-3 TLE Series 625 - 750 - 1000 – Power connection configuration bus bars with top cable entry (standard)
Power connection cables are connected to bus bars using M12 bolts.
The bolts of the connection cables must be tightened with a torque wrench at 530 Lb-in / 60 Nm.
TLE Series 625 & 750
TLE Series 1000
Fig. 4.9-4 TLE Series 625 - 750 - 1000 - Power connection configuration bus bars with bottom cable entry
Modifications reserved
GE_UPS_ISG_TLE_SUL_M62_1M0_2US_V010.docx
Critical Power
Top entry cables
Utility input & Load output
Q1
Top entry cables
Utility input & Load output
Q1
Q1
Bottom entry cables
Utility input & Load output
Q1
Bottom entry cables
Utility input & Load output
BR3
Load
L3
L3-1
Load
L2
L2-1
BR1
Load
L1
L1-1
cables input from the top of the UPS
Position of the bus bars for
cables input from the bottom of the UPS
BR3
L3-1
Load
L3
BR2
Load
L2
L2-1
BR1
Load
L1-2
L1
L1-1
Installation Guide TLE Series 625 - 750 - 1000 UL S2
L3-2
N
BR2
L2-2
N
L1-2
Position of the bus bars for
L3-2
N
L2-2
N
Page 42/69

Advertisement

Table of Contents
loading

Table of Contents