TLE Series 300 - 400 - 500 Access to the bus bars for the cable connections
A
To access Input, Output and Battery connections
proceed as follows:
Remove the front protection panel "A".
Bottom entry cables: remove the plate "B".
Top entry cables: remove the plate "C".
CAUTION !
Panel "A, B and C" should never be removed or replaced with power applied to the
UPS.
These panels are in close proximity to 480V live buss bars.
Always disconnect the rectifier, bypass, load and battery sources from the UPS
before removing or replacing these panels.
If not serious injury or death could occur!
Modifications reserved
GE_UPS_ISG_TLE_SUL_M16_M50_2bU_V010.docx
Critical Power
Utility mains / Battery / Output load
Please remove
the plates (B & C) before
drilling any wholes
Fig. 4.8-2 TLE Series 300 - 400 - 500 Access to connection bus bars
C
Utility mains / Battery / Output load
Top entry cables
Q1
Bottom entry cables
NOTE !
For
operation,
utility phase rotation
must be clock-wise.
Installation Guide TLE Series 160 - 500 UL S2B