5. Lay a straightedge from the forward top roller to the idler.
Fig. 5-112
6. Measure the gap at location (1) (to the top of the track shoe).
7. Lay a straightedge from the rear top roller to the final drive sprocket.
Fig. 5-113
8. Measure the gap at location (2) (to the top of the track shoe).
9. Add dimensions (1) and (2).
NOTE: The total should be 3–4 in. (76.2–101.6 mm).
10. Adjust the track tension as needed.