Commissioning
The gas pressures must be checked against those printed on the data plate of the appliance. The
pressures are factory set and may not require adjustment. When checking the operating pressures
the combustion chamber glass must be on.
The commissioning sheet is located in a plastic pouch inside the unit on top of the PCB cover.
Follow the commissioning instructions to complete the gas pressure checks. When commissioning
is complete check for full and correct operation of the appliance, and return the commissioning
sheet to its plastic pouch.
24 | Novo freestanding installation guide:13992-A 01-22
Pilot pressure test point screw
Main burner pressure test point screw
Inlet pressure test point screw
Pilot pressure adjustment screw