Commissioning
The gas pressures must be checked against those printed on the data plate* of the
appliance. The pressures are factory set and may not require adjustment. When
checking the operating pressures the combustion chamber glass must be on.
* Location of the data plate is on the base plate of the engine, within the air gap on the RHS of the appliance.
Commissioning sheet
The commissioning sheet is located in a plastic pouch, inside the unit, on top of the
PCB cover. Follow the commissioning instructions to complete the gas pressure checks.
When commissioned, check for full and correct operation of the appliance, and place the
commissioning sheet back inside the plastic pouch.
Commissioning sheet located
on top of the PCB cover
Burner pressure
test point screw
Manometer position
for pilot pressure
Pilot pressure adjustment
screw
Gas control
Inlet pressure test
point screw
Neo RIB2312 installation guide: 12148-D 04-19 | 25