Unpack the fire
1. Remove the frame (two screws).
2. Remove the control panel (two screws) and
unplug the ON/OFF switch.
3. Remove the mounting plate (two screws)
and lift the fire off the plate.
Fix the mounting plate to the floor
1. Mark the position of the flue centreline on
the floor. Note the minimum distance from
the wall (50 mm). This is required to allow
the back panel of the fire to be fitted to the
mounting plate.
2. The gas and power supply can be brought
in through the base of the fire. The pipe/
power cord must enter within the shaded area
shown on the next page. The hole can be
bigger, but must not extend beyond the fire
footprint. If the power is to be brought in from
12 | Novo freestanding installation guide:13992-A 01-22
1
3
2
the back, there is a knockout in the bottom
right corner (viewed from the back of the fire)
of the back panel that can be removed with
pliers. There is also a knockout for the gas on
the back panel.
3. Fix the mounting plate to the floor using a
minimum of four screws (not supplied). For
seismic restraint each fixing must be capable
of withstanding a pull force of 1.5 kN. A 10 ga
screw 35 mm into solid timber (this may mean
solid blocking is required under the floor), or a
8 mm dynabolt type masonry fastener.
Check the flue configuration
Check the flue configuration, do the aeration
plates need adjusting or additional plates
added? Refer to page 14 for more information.
Install the fire back onto the mounting plate
Follow the reverse steps for unpacking the fire.