The chapter "Safety instructions" must be heeded.
Before the separator is put into operation, please make sure
6.1 Setting up for operation
that:
the separator is clean and the interior is free from any
objects which may have been placed inside during ship-
•
ping or installation.
the separator is completely filled with clean cold water.
Completely filling the separator is complete when water
•
begins to drain from the outlet.
6.2 Initial Instructions
Placing the separator into full operation is normally handled
by a licensed tradesman although upon request can be hand-
led by a KESSEL representative.
The following personnel should be on hand when the initial
instructions for placing the separator into operation are given:
Building facilities manager
Building maintenance workers
•
Contracted plumber / tradesman
•
Contracted disposal company
•
•
6. Commissioning
What to do:
Check to make sure the separator is completely water-
tight. Check to make sure that during transport and in-
•
stallation that no damage to the separator was caused.
Check to make sure all connections to the
separator (inlet, outlet, refill, rinse pipes etc.) are in per-
fect working order.
Representative should discuss all necessary information
regarding the disposal.
•
Representative should take the customer step by step
through all stages of a separator disposal.
•
After the separator has been emptied (disposed) all ne-
cessary paperwork and documentation should be han-
•
ded over to the customer.
The separator should be returned to service by filling the
separator with fresh, cold water.
•
6.3 Commissioning report (see attachment)
39