Indigo NXT QuietQube/CVD: Sequence of Operation
Harvest – Condensing Unit
1
2
Purge
Equalize
45 Sec
5 Sec
Suction Pressure remains higher than the low
pressure control cut-out (12 psig) and the
compressor continues to run.
Discharge pressure remains below the fan cycle
control cut-out setting and the condenser fan
motor remains off.
3
Pre-Chill
Start
120 Sec.
Ice Thickness
5 Sec
(first cycle)
30 Sec.
(thereafter)
Harvest
4
5
Freeze
Purge
45 Sec
Probe
7 Minute Max
Discharge
Gas
6
Harvest
Bin Switch
Discharge
Gas to
Receiver
88