To ground the chassis:
1 Locate the grounding point on the back of the chassis
Figure 32: Grounding Point on BlackDiamond 10808 Chassis
Power supply
controllers
2 Strip 0.5-inch (1.2-cm) of insulation from the stranded copper wire cable.
3 Insert the stripped wire into the cable lug.
CAUTION
Be sure that no copper is visible between the lug and the cable insulation.
4 Crimp the lug onto the cable according to the manufacturer's specifications.
5 Insert the screws through the lug and into the grounding point on the back of the chassis.
6 Connect the other end of the wire to a known reliable earth ground point at your site.

Initial Management Access

After your switch has completed all power on self-tests, it is operational. You can log in and configure
an IP address for the default VLAN (named default).
NOTE
In BlackDiamond switches, the management port on the MSM is part of the management VLAN by default. Refer to
"Management Ports" on page 14
BlackDiamond 10808 Switch Hardware Installation Guide
for further details.
Initial Management Access
(Figure
32).
Grounding
point
EX_007A
69