Click "Start" to enter the commissioning function and the software automatically performs
commissioning. "
" indicates that commissioning is being performed on the phase and "
indicates that commissioning is passed on the phase.
For the phase with "OK" displayed, a manual confirmation is required for entering the next
commissioning step. Click "
references for selection. Click "Close" to close the information (the number of commissioning units is
displayed in "3 Confirm ODU Basic Module NO." and "4 Confirm IDU NO."; the preheating period is
displayed in "8 Compr. Preheat Confirmation").
GMV5E DC INVERTER VRF UNITS SERVICE MANUAL
" to display relevant information detected on this phase, which provides
115
"