Terminal Test; Output Test - Siemens SIGMAGYR RVP540 Basic Documentation

Heat energy manager
Hide thumbs Also See for SIGMAGYR RVP540:
Table of Contents

Advertisement

Benefit
Description
Setting
Effect
Display
Timeout
128/348
Siemens Building Technologies
HVAC Products

Terminal test

4.49 Output test

• Connections can be checked prior to commissioning
• Wiring errors can be pinpointed very rapidly
The output test can be used for checking the wiring.
It is also termed relay test.
Setting range
--- / 0...10
The output test will automatically become available on this operating line.
With each test step, the respective output will be activated so that it can be checked. By
pressing the + / - buttons, it is possible to change from one test step to the next.
---
No test
Test step 0
All outputs (Q101...Q110) are deactivated
Test step 1
Output Q101 activated
Test step 2
Output Q102 activated
Test step 3
Output Q103 activated
Test step 4
Output Q104 activated
Test step 5
Output Q105 activated
Test step 6
Output Q106 activated
Test step 7
Output Q107 activated
Test step 8
Output Q108 activated
Test step 9
Output Q109 activated
Output Q110 activated
Test step 10
1 2
3 4
5
6
c)
4
8
0
a) The pointer below the symbol indicates the output activated
b) The number indicates the current test step
c) The framed number indicates the selected setting line
When there is no operating action, the output test will automatically be quit after 8 min-
utes.
Basic Documentation RVP540 / RVP550
Description of the heating engineer settings
Unit
Increment
(all outputs switch according to the current operating state)
7 8
9 10
12
16
20
24
Factory setting
- - -
a)
b)
CE1P2488en
18.10.2002