3.3 Parallel System Installation
3.3.1 Installing the UPSs
Context
When installing multiple cabinets, install connecting kits to combine and secure the cabinets.
Procedure
Step 1 Install the UPSs in a parallel system using the single UPS installation method.
Step 2 Install connecting kits for the cabinets.
Issue 05 (2019-12-24)
When the EPO switch is in the NC state, remove the jumper between EPO_NC and EPO_12V
before connection. When the EPO switch is turned off, EPO is triggered.
When the EPO switch is in the NO state, ensure that the jumper is connected between EPO_NC and
EPO_12V. When the EPO switch is turned on, EPO is triggered.