Connect cables from bottom up in this sequence: bypass input power cables, output power
cables, mains input power cables, and battery input power cables.
When connecting cables, tighten bolts from inside out to secure cables.
Before connecting cables, ensure that all UPS input switches are turned off. Paste warning
labels to prevent others from operating the switches.
Connect the input power cables to the UPS before connecting power cables to customer
equipment.
Figure 3-28 Grounding
Step 6 Connect the bypass input power cables. (Perform this step only when the mains input and
bypass input use different power sources.)
Issue 05 (2019-12-24)