5 Installation and startup

5.5 Repacking

36
Ä If no hub is found in the network, you can manually enter the IP
settings.
4. Confirm the date and time.
5. Activate the suction settings if necessary.
6. Press the "Back" button to change a setting or press "Save" to
conclude setup.
Switching the unit off
ü The unit has finished the machining operation.
➢ Press the On/Off button on the front.
Ä The unit then switches off. The On/Off button changes from green
to blue.
Repacking
5.5
NOTE
Repack only drained units!
Drain the unit!
ü The water tank is empty.
ü The main switch on the back side of the unit is set to the 0 (OFF)
position.
1. Disconnect the power cable and the connecting cable from the back
side of the unit and stow them away.
2. Stow away the calibration tools in the drawer.
3. Check the unit for completeness according to the scope of supply!
4. Pack the unit securely.

Scope of supply

5.6
The detailed scope of supply is specified in the document "Checklist
CEREC Primemill".

Storage

5.7
NOTE
Repack only drained units!
Drain the unit! See "Removing water from the unit  [→ 59]".
Store the unit in a closed and dry room at a temperature of -40 °C
(-40 °F) to 70 °C (158 °F).
Dentsply Sirona
Operating Instructions CEREC Primemill
67 19 681 D3439
D3439.201.01.01.02    09.2019

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cerec primemill us

Table of Contents