Part II: NE provisioning and stand-alone
installation test
Overview
...................................................................................................................................................................................................................................
Purpose
This part of the 1675 LambdaUnite MSS Installation Guide contains the NE
provisioning and the stand-alone test procedures.
Contents
This part of the document contains the following chapters:
• Chapter 7,
NE provisioning
• Chapter 8,
Stand-alone test procedures
• Chapter 9,
Exit checklist – Part II
Entry checklist
The following provides a checklist to be completed prior to performing the NE
provisioning and stand-alone installation tests. Verify that each procedure has been
completed. Check off and initial the item.
Procedure
Have all procedures been completed which
are required in chapter 6,
power installation exit checklist" (p.
Is a CAT5 crossover LAN cable with
RJ-45/RJ-45 connectors available (see
chapter 4,
Figure 4-48, "CIT connection
(LAN crossed)" (p.
....................................................................................................................................................................................................................................
365-374-179R10.0
Issue 2, June 2009
"Physical and
6-2)?
4-73))?
Alcatel-Lucent - Proprietary
Completed
See notice on first page
Initials
Notes
II-1