NOTE: The Storage Tank will have a minor amount of
pressure. Some water will exit the hole when the
fitting is removed.
6. CLOSE the Soft Water Inlet Valve.
10
Flush Everpure Postfilter Cartridge
Switch and Valve Starting Positions:
• System Power - Off
• Storage Tank Power - Off
• Soft Water Inlet Valve - Closed
• Hard Water Inlet Valve - Closed
• Hard Water Blend Valve - Open
• Blended Water Outlet Valve - Closed
1. Connect 1/2-inch O.D. tubing to the Blended Water Outlet
Valve. Route this tubing to a drain.
2. OPEN the Hard Water Inlet Valve (Figure 14).
Hard Water
Blend Valve
Hard Water
Inlet Valve
NOTE: Cartridges not shown.
Figure 14
3. OPEN the Blended Water Outlet Valve (Figure 14). Flush
the SEN Postfilter Cartridge(s) to drain for five (5)
minutes.
4. CLOSE the Hard Water Inlet Valve.
5. Remove the tubing from the Blended Water Outlet Valve.
6. Plug the Storage Tank Permeate Pump into the
connection at the bottom of the HE-3 System frame.
16
WATER YOU CAN TRUST
Blended Water
Outlet Valve
®
11
Adjust The Blending Valves
There are two (2) valves that are adjustable to provide a blend
of RO permeate and incoming water to suit the application.
RO Blend Valve
Hard Water
Blend Valve
Soft Water
Inlet Valve
Hard Water
Inlet Valve
Figure 15
To adjust the blend:
1. Determine the desired TDS for the application.
2. Locate the two (2) Blend Valves above the filter
manifolds.
3. OPEN the RO Blend Valve fully, see Figure 15. This allows
maximum flow of the RO permeate water.
4. CLOSE the Hard Water Blend Valve, see Figure 15.
NOTE: This configuration provides only RO permeate water
with no hard water blend.
5. OPEN the Hard Water Blend Valve one (1) full rotation.
6. OPEN the Soft Water and the Hard Water Inlet Valves.
7. With the system turned ON, run water out of the Blended
Water Outlet Valve for two (2) minutes.
8. Test the TDS or check the post-filter status screen.
9. If the TDS is too high, then CLOSE the Hard Water Blend
Valve in small increments and retest. If the TDS is too
low, then OPEN the Hard Water Blend Valve in small
increments and retest. Allow water to flow for two (2)
minutes between tests.
10. When the blend is correct, mount and secure the HE-3
Processor Cover. Place the system into full operation.
Blended
Water Outlet
Valve