Phase-To-Phase Faults; Phase-To-Earth Faults - ABB RELION REG670 Commissioning Manual

Generator protection
Hide thumbs Also See for RELION REG670:
Table of Contents

Advertisement

Section 12
Testing functionality by secondary injection
12.4.3.1

Phase-to-phase faults

IEC07000009 V4 EN-US
Figure 37: Proposed test points for phase-to-phase fault
Table 21:
Test
points
1
2
3
Change the magnitude and angle of phase-to-phase voltage to achieve impedances at test
points 1, 2 and 3. For each test point, observe that the output signals, START, STLx and STPP
are activated where x refers to the actual phase to be tested. After the timer
zone has elapsed, also the signals TRIP, TRPP and TRx shall be activated.
12.4.3.2

Phase-to-earth faults

For simplicity, the same test points as for phase-to-phase faults are proposed, but
considering new impedance values.
110
X
3
50%
ZAngPP
Test points for phase-to-phase (ohms / phase)
reach
Value
X
ZPP · sin(ZAngPP)
R
ZPP · sin(ZAngPP)
X
0,5· (ZPP· sin(ZAngPP)
R
0,5·ZPP + ΔR = 0,5·ZPP·(1+cos(ZAngPP))
X
0,5·ZPP·sin(ZAngPP)
R
0,5·ZPP - ΔR = 0,5·ZPP(1-cos(ZAngPP))
1
ZPP
2
R
Ohm/phase
IEC07000009-4-en.vsd
1MRK 502 067-UEN B
Comments
tPP for the actual
Commissioning manual
M14944-292 v8