Section 7
Calibrating injection based 100% stator earth fault protection
GUID-3C378090-E33E-4AAA-8BBE-09FA872D9A87 V1 EN-US
Figure 20: ICT toolbar
5.
Select the Installing tab if it was not already selected by default after the ICT was
launched.
The first thing that needs to be ensured before the calibration is that the measured
voltage and current signal at the injected frequency is present/found, and that their
amplitude is within the permitted limits.
6.
Write the value "UMaxEF" according to the setting in REX060. Select the Start reading
values from IED button from the ICT toolbar to start performing continuous
measurements.
7.
Verify that the bars/voltage levels for both the voltage and current on the injected
frequency have acceptable level.
The bars must be green and the function status field must also indicate OK.
8.
Check that the actual injected frequency is close enough to the injection frequency set on
the injection unit (REX060).
If the voltage and/or current level(s)/frequencies are not reasonable, or the ICT indicates
other warnings/abnormalities in the function status field, verify that the HW connections
are correct (cables etc.), and selected UMaxEF and injection frequency on the REX060 are
properly set. Then repeat steps 3 to 6. Note that the
setting for the specific function must correspond with the chosen injection frequency on
the REX060 HMI for that function.
GUID-84947C77-215F-4007-AAC0-9433B8444396 V1 EN-US
Figure 21:
9.
When the installing procedure is successful, select the Submit and save in report button.
ICT will now forward a more accurate frequency to
setting tool, write the newly acquired parameter to IED.
The accurate setting of this frequency is essential for proper operation of the protection
under different operating conditions.
7.4

Performing calibration

1.
From the Calibrating tab, select the first sub tab, i.e. Step1: Measurement 1.
2.
Make sure you have not attached any additional impedance in parallel with the stator.
The generator shall be in a condition that is as close as possible to the normal operating
condition as during the Installation.
3.
From the ICT toolbar, select the Start reading values from IED button.
ICT now performs continuous measurements and after the tenth measurement it starts
to update the graph. Notice that the stability region indicator bar reduces in size.
66
Function selection
dropdown menu
Frequency found by
Voltage and current signal
the function
staus and TRIP indication
ICT signals and function indication panel
Button for
Buttons for start/stop
enable/disable
reading from IED
tripping
IEC11000043-1-en.vsd
FreqInjected setting in Parameter
Ffunction status field. Errors and
abnormalities are displayed in order
to simplify trouble shooting.
IEC11000045-1-en.vsd
Parameter setting . In the Parameter
1MRK 502 067-UEN B
GUID-9304B342-8BCF-49E3-8429-E64919DC8EBD v4
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents