1MRK 502 067-UEN B
12.5.13.2

Completing the test

Continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
12.5.14

Directional overpower protection GOPPDOP

Prepare the IED for verification of settings as outlined in section
section
12.5.14.1

Verifying the settings

The overpower protection shall be set to values according to the real set values to be used. The
test is made by means of injection of voltage and current where the amplitude of both current
and voltage and the phase angle between the voltage and current can be controlled. During the
test the analog outputs of active and reactive power shall be monitored.
1.
Connect the test set for injection of voltage and current corresponding to the mode to
be used in the application. If a three phase test set is available this could be used for all
the modes. If a single phase current/voltage test set is available the test set should be
connected to a selected input for one phase current and voltage.
2.
Adjust the injected current and voltage to the set rated values in % of
(converted to secondary current and voltage). The angle between the injected current
and voltage shall be set equal to the set direction
low forward power protection and equal to 180° for reverse power protection). Check
that the monitored active power is equal to 100% of rated power and that the reactive
power is equal to 0% of rated power.
3.
Change the angle between the injected current and voltage to
the monitored active power is equal to 0% of rated power and that the reactive power is
equal to 100% of rated power.
4.
Change the angle between the injected current and voltage back to
the current slowly from 0 until the START1 signal, start of stage 1, is activated. Check the
injected power and compare it to the set value
Sbase .
5.
Increase the current to 100% of
6.
Switch the current on and measure the time for activation of TRIP1, trip of stage 1.
7.
If a second stage is used, repeat steps
12.5.14.2
Completing the test
Continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
12.5.15

Broken conductor check BRCPTOC

Prepare the IED for verification of settings as outlined in section
section
12.5.15.1

Measuring the operate and time limit of set values

Commissioning manual
"Preparing for test"
in this chapter.
"Preparing for test"
in this chapter.
Angle1 , angle for stage 1 (equal to 0° for
Power1 , power setting for stage 1 in % of
IBase and switch the current off.
2
to
6
for the second stage.
Testing functionality by secondary injection
TestMode setting to Off .
"Requirements"
and
IBase and UBase
Angle1 + 90°. Check that
Angle1 value. Increase
TestMode setting to Off .
"Requirements"
and
Section 12
SEMOD175027-15 v4
SEMOD175058-3 v5
SEMOD175058-7 v6
SEMOD175058-66 v4
SEMOD175021-3 v5
SEMOD175021-7 v6
175

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents