Completing The Test; Phase Selection With Load Encroachment, Quadrilateral Characteristic Fdpspdis - ABB RELION REG670 Commissioning Manual

Generator protection
Hide thumbs Also See for RELION REG670:
Table of Contents

Advertisement

Section 12
Testing functionality by secondary injection
1.
Subject the IED to healthy normal load conditions for at least two seconds.
2.
Apply the fault condition to find the operating time for the phase-to-phase fault
according to test point 12 in figure
measurement with the setting
3.
Repeat steps 1 to 2 to find the operating time for the phase-to-earth fault according to
test point 12 in figure
setting
4.
Repeat steps 1 to 3 to find the operating time for all other used measuring zones.
Observe that the zones that are not tested have to be blocked and the zone that is tested
has to be released.
12.4.1.3

Completing the test

Continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
12.4.2
Phase selection with load encroachment, quadrilateral
characteristic FDPSPDIS
Prepare the IED for verification of settings outlined in section "Requirements" and
section "Preparing for test" in this chapter.
The phase selectors operate on the same measuring principles as the impedance measuring
zones. So it is necessary to follow the same principles as for distance protection, when
performing the secondary injection tests.
Measure operating characteristics during constant current conditions. Keep the measured
current as close as possible to the rated value of its associated input transformer, or lower.
But ensure that it is higher than the set minimum operating current.
Ensure that the maximum continuous current to the IED does not exceed four times its rated
value, if the measurement of the operating characteristics runs under constant voltage
conditions.
To verify the settings the operating points according to figures
See also tables
106
34
and table 18. Compare the result of the measurement with the
t1PE .
19
and
20
for information.
33
and table
17
for zone 1. Compare the result of the
t1PP .
1MRK 502 067-UEN B
TestMode setting to Off .
35
and
36
should be tested.
Commissioning manual
M14944-167 v3
M13906-3 v9

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents