Procedure
1. Select the OPC server in HW Config, and then select the menu command Edit > Object
Properties....
The "Properties – OPC server" dialog box opens.
2. Open the "SNMP" tab.
3. Enter at least 1000 ms in the "Cycle time" input box.
You can obtain additional information with the "Help" button.
4. Click "Edit plant configuration".
The "Edit plant configuration" dialog box opens.
5. Click "Import".
All objects configured in your project with an IP address are imported.
Note
When you import a CP 1623 / CP 1613, the IP address of the HW Config is imported. If
necessary, replace this TCP/IP address with an NDIS IP address.
6. Double-click the node.
The "Edit node" dialog box opens.
7. Enter the following data for the imported devices.
– Name:
– IP address:
– Device profile and community:
– Timeout:
– SNMP optimization
– Comment:
8. Click "OK".
The "Edit nodes" dialog box closes and you return to the "Edit plant configuration" dialog
box.
Maintenance Station
Function Manual, 03/2016, A5E36187641-AA
5.9 Configuring the monitoring of industrial PCs and network objects
Enter a name.
If necessary, change the IP address.
You can find additional information about this in the section "Device profiles and
community (Page 45)".
Note
Note that these community name entries are case sensitive.
The community name in the "Edit Node" and "Add Node" dialog boxes must match the
community name stored in the respective device.
Enter a value of 9000 ms or higher, depending on the number of components to be
monitored.
You can obtain additional information with the "Help" button.
Activate the check box.
You can enter a comment in this field. This comment is visualized in the faceplate of the
process control system.
Configuring the maintenance stations