SECTION 4 - BOOM & PLATFORM
12. Install the bolt, keeper pin, upper and lower pivot pin
securing the platform pivot to the channel and jib cylin-
der assembly.

Installation

1. Using adequate lifting support, lift the boom into posi-
tion on the machine. Install the pivot pin, keeper pin,
and bolt securing the boom to the upright.
NOTE: The main boom weighs approximately 1451 lbs. (435 kg).
4-10
2. Install the pivot pin, nut, and bolt securing the top of the
timing link to the boom.
MAE30290
3. Install the pivot pin, keeper pin, and bolt securing the
rod end of the lift cylinder to the boom.
4. Connect the hydraulic hoses at the rear of the telescope
cylinder as tagged during removal.
5. Install the master cylinder. Refer Section 4.6, Master Cyl-
inder.
6. Operate the boom through all functions and check for
proper operation or any leakage.
MAE29050
3121200