SM60A connect (without meter plug), if applicable:
NOTE: Meter 5, 6 connect the RJ45 3, 6, then RJ45 connect the cable
box/super cable box.
For AC/Hybrid system, there are two meter needed:
Option 1: with Meter Plug
Figure 43 Two Meter Connect, with Meter
Plug
2.3.3
Backup Box (If Applicable)
Backup Box Connect to SMILE5 (single-phase grid in house):
GRID
PV-INV
PV
Figure 45 Backup Box Connect to SMILE5 (single phase grid in house)
___________________________________________________________________
Figure 42 SM60A connect (without meter plug)
COM
GRID_L1
LOAD_L1
PV-INV_L1
AC_L1
BAK_L1
GRID_L2
L
LOAD_L2
PV-INV_L2
N
AC_L2
GRID_L3
BAK_L2
PE
PV-INV_L3
LOAD_L3
AC_L3
GRID_N
BAK_L3
L
PV-INV_N
meter
LOAD_N
N
AC_N
GRID_PE
BAK_N
PV-INV_PE
DSP_BackupBox
Alpha ESS Co., Ltd.
Option 2: without Meter Plug
Figure 44 Two Meter Connect, without Meter
Plug
patch cable
LOAD3
LOAD2
RCD
L
N
AC
Storion-S5
PE
ECO-ES5
SMILE5
L
N
BACK
Meter Port
PE
Bat
Your Smart Energy
LOAD1
PV
patch cable
Page 26 of 40