CAUTION!
When removing the cover, make sure not to damage the internal components. SolarEdge will not be held
responsible for any components damaged as a result of incautious cover removal.

Step 1: Activating the System

 1.  Verify that the inverter ON/OFF switch is OFF.
 2.  Verify that the StorEdge Connection Unit switch is in the OFF position. 
 3.  Remove the inverter cover: Open the inverter cover's six Allen screws and carefully pull the cover 
horizontally before lowering it.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when the inverter cover is
removed.
Activate the inverter:
 4. 
 a.  Verify that the card S/N matches the inverter S/N.
 b.  Insert the card into the "CARD" slot on the communication board.
 c.  Turn ON   t he AC switch of the main circuit board.
 d.  LCD shows: Running Script... Done!
If LCD shows: Failed:
Turn AC OFF and ON (reset), and repeat the activation process.
 
Use the activation code that appears on the certification inverter label to manually activate the 
 
inverter.
If the problem persists, contact SolarEdge Support.
 
NOTE
You can use the activation code that appears on the certification inverter label to 
activate the inverter in case of a script error or a missing activation card.
 5.  Verify that the inverter is configured to the proper country: Press the LCD light button until reaching 
the ID status screen: 
I D :
# # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
StorEdge Inverter Installation Guide MAN-01-00390-1.1
Figure 31: Activation card
# #